ONSHORE WIND · ISO-NEDeerfield Wind
Deerfield Wind is a 30.0 MW onshore wind request withdrawn in the ISO-NE interconnection queue, in Bennington County, Vermont.
Queue statusWithdrawn / abandoned
- PlanningQueued Sep 2008 (completed)
- Withdrawn / abandonedSep 2014 (project stopped here)
- Consented (not reached)
- Construction (not reached)
- Operating (not reached)
- Closed (not reached)
Request details
- Queue ID
- 276
- Grid region
- ISO-NE (New England)
- Connection point (POI)
- Y-25 North, 69 kV line between Searsburg and Benni
- Location
- Bennington County, Vermont
- Technology
- Wind: 30.0 MW
- Total requested
- 30.0 MW
- Service type
- Energy only (ERIS)
- Study phase
- Executed
- Queue status
- Withdrawn
- Entered queue
- 2 September 2008
- Proposed online date
- December 2013
- Withdrawn
- September 2014
Location
Marker shows the centre of Bennington County; the queue data does not give exact sites.
Other requests in Bennington County
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem