United States βΊ Grid βΊ Interconnection queues βΊ Vermont
ONSHORE WIND Β· ISO-NEWind Project
Wind Project is a 48.0 MW onshore wind request withdrawn in the ISO-NE interconnection queue, in Windham County, Vermont.
Queue statusWithdrawn / abandoned
- PlanningQueued Dec 2005 (completed)
- Withdrawn / abandonedApr 2006 (project stopped here)
- Consented (not reached)
- Construction (not reached)
- Operating (not reached)
- Closed (not reached)
Request details
- Queue ID
- 142
- Grid region
- ISO-NE (New England)
- Connection point (POI)
- CVPS Londonderry Substation 46 kV
- Location
- Windham County, Vermont
- Technology
- Wind: 48.0 MW
- Total requested
- 48.0 MW
- Service type
- Other
- Queue status
- Withdrawn
- Entered queue
- 21 December 2005
- Proposed online date
- May 2008
- Withdrawn
- April 2006
Location
Marker shows the centre of Windham County; the queue data does not give exact sites.
Other requests in Windham County
- VT Yankee Nuclear Power Station Upgrade7Nuclear Β· 642 MW Β· built
- Vernon RepoweringHydro Β· 32.0 MW Β· built
- Vernon Station Incremental Capacity IncreaseHydro Β· 2.9 MW Β· built
- Battery StorageBattery storage Β· 101 MW Β· withdrawn
- WindOnshore wind Β· 73.5 MW Β· withdrawn
- SolarSolar Β· 20.0 MW Β· withdrawn
- SolarSolar Β· 8.1 MW Β· withdrawn
- SolarSolar Β· 2.2 MW Β· withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem