πŸ”Œ EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more β†’ Skip to main content

United States β€Ί Grid β€Ί Interconnection queues β€Ί Vermont

SOLAR Β· ISO-NE

Solar

Solar is a 2.2 MW solar request withdrawn in the ISO-NE interconnection queue, in Windham County, Vermont.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Jul 2012 (completed)
  2. Withdrawn / abandonedOct 2012 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
395
Grid region
ISO-NE (New England)
Connection point (POI)
CVPS 46 kV
Location
Windham County, Vermont
Technology
Solar: 2.2 MW
Total requested
2.2 MW
Service type
Network resource (NRIS)
Queue status
Withdrawn
Entered queue
30 July 2012
Proposed online date
June 2013
Withdrawn
October 2012

Location

Marker shows the centre of Windham County; the queue data does not give exact sites.

Power plants in Vermont Β· Transmission lines in Vermont

Other requests in Windham County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem