SOLAR Β· ISO-NEDavenport Solar
Davenport Solar is a 15.0 MW solar request withdrawn in the ISO-NE interconnection queue, in Rutland County, Vermont.
Queue statusWithdrawn / abandoned
- PlanningQueued Apr 2018 (completed)
- Withdrawn / abandonedJun 2022 (project stopped here)
- ConsentedOct 2020 (not reached)
- Construction (not reached)
- Operating (not reached)
- Closed (not reached)
Request details
- Queue ID
- 763
- Grid region
- ISO-NE (New England)
- Connection point (POI)
- Florence - S. Middlebury Jct. 46 kV line, approx. 4 miles from Florence
- Location
- Rutland County, Vermont
- Technology
- Solar: 15.0 MW
- Total requested
- 15.0 MW
- Service type
- Energy only (ERIS)
- Study phase
- Executed
- Queue status
- Withdrawn
- Entered queue
- 27 April 2018
- Agreement signed
- 20 October 2020
- Proposed online date
- December 2021
- Withdrawn
- June 2022
Location
Marker shows the centre of Rutland County; the queue data does not give exact sites.
Other requests in Rutland County
- Fair Haven SolarSolar Β· 20.0 MW Β· agreement signed
- Proctor Hydroelectric Station UprateHydro Β· 3.2 MW Β· built
- WindOnshore wind Β· 85.0 MW Β· withdrawn
- Wind ProjectOnshore wind Β· 60.0 MW Β· withdrawn
- Fair Haven BiomassOther Β· 33.0 MW Β· withdrawn
- SolarSolar Β· 22.5 MW Β· withdrawn
- Grandpas Knob WindOnshore wind Β· 20.0 MW Β· withdrawn
- SolarSolar Β· 20.0 MW Β· withdrawn
- SolarSolar Β· 19.9 MW Β· withdrawn
- HydroHydro Β· 1.3 MW Β· withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem