United States › Grid › Interconnection queues › Vermont
ONSHORE WIND · ISO-NEGrandpas Knob Wind
Grandpas Knob Wind is a 20.0 MW onshore wind request withdrawn in the ISO-NE interconnection queue, in Rutland County, Vermont.
Queue statusWithdrawn / abandoned
- PlanningQueued Mar 2011 (completed)
- Withdrawn / abandonedMay 2014 (project stopped here)
- ConsentedOct 2013 (not reached)
- Construction (not reached)
- Operating (not reached)
- Closed (not reached)
Request details
- Queue ID
- 361
- Grid region
- ISO-NE (New England)
- Connection point (POI)
- VELCO W Rutland 115 kV Substation
- Location
- Rutland County, Vermont
- Technology
- Wind: 20.0 MW
- Total requested
- 20.0 MW
- Service type
- Energy only (ERIS)
- Study phase
- Executed
- Queue status
- Withdrawn
- Entered queue
- 14 March 2011
- Agreement signed
- 15 October 2013
- Proposed online date
- December 2016
- Withdrawn
- May 2014
Location
Marker shows the centre of Rutland County; the queue data does not give exact sites.
Other requests in Rutland County
- Fair Haven SolarSolar · 20.0 MW · agreement signed
- Proctor Hydroelectric Station UprateHydro · 3.2 MW · built
- WindOnshore wind · 85.0 MW · withdrawn
- Wind ProjectOnshore wind · 60.0 MW · withdrawn
- Fair Haven BiomassOther · 33.0 MW · withdrawn
- SolarSolar · 22.5 MW · withdrawn
- SolarSolar · 20.0 MW · withdrawn
- SolarSolar · 19.9 MW · withdrawn
- Davenport SolarSolar · 15.0 MW · withdrawn
- HydroHydro · 1.3 MW · withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem