ONSHORE WIND Β· ISO-NE

Wind

Wind is a 85.0 MW onshore wind request withdrawn in the ISO-NE interconnection queue, in Rutland County, Vermont.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Oct 2008 (completed)
  2. Withdrawn / abandonedMar 2010 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
281
Grid region
ISO-NE (New England)
Connection point (POI)
VELCO 115 kV K34 line
Location
Rutland County, Vermont
Technology
Wind: 85.0 MW
Total requested
85.0 MW
Service type
Network resource (NRIS)
Study phase
Feasibility Study
Queue status
Withdrawn
Entered queue
6 October 2008
Proposed online date
September 2011
Withdrawn
March 2010

Location

Marker shows the centre of Rutland County; the queue data does not give exact sites.

Power plants in Vermont Β· Transmission lines in Vermont

Other requests in Rutland County