Fair Haven Biomass

Fair Haven Biomass is a 33.0 MW other request withdrawn in the ISO-NE interconnection queue, in Rutland County, Vermont.

Queue statusWithdrawn / abandoned
  1. PlanningQueued May 2010 (completed)
  2. Withdrawn / abandonedJun 2015 (project stopped here)
  3. ConsentedJul 2012 (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
330
Grid region
ISO-NE (New England)
Connection point (POI)
CVPS 46 kV Castleton - Fair Haven
Location
Rutland County, Vermont
Technology
Other: 33.0 MW
Total requested
33.0 MW
Service type
Energy only (ERIS)
Study phase
Executed
Queue status
Withdrawn
Entered queue
10 May 2010
Agreement signed
18 July 2012
Proposed online date
March 2016
Withdrawn
June 2015

Location

Marker shows the centre of Rutland County; the queue data does not give exact sites.

Power plants in Vermont Β· Transmission lines in Vermont

Other requests in Rutland County