Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown6710.4 GW
Active in queue26.4 GW108 requests
Agreement signed14.2 GW51 requests
Withdrawn6710.4 GW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

67 requests · page 1 of 2
ProjectCapacityStatusLocationRegionQueuedOnline
Gibbons Creek TEERP
Coal · TEERP Power Station LLC
420 MWWithdrawn / abandoned Grimes, TXERCOT Apr 2020target 2020
Plum Creek Solar I
Solar · PLUM CREEK SOLAR I, LLC
400 MWWithdrawn / abandoned Grimes, TXERCOT Jun 2020target 2023
BRP Pobeda BESS
Battery storage · BRP Pobeda BESS LLC
301 MWWithdrawn / abandoned ERCOT Nov 2020target 2028
Sibyl Power Station
Gas · WattBridge Energy, LLC
299 MWWithdrawn / abandoned Fort Bend, TXERCOT Sep 2020target 2025
BRP Denali BESS
Battery storage · BRP Denali BESS LLC
258 MWWithdrawn / abandoned ERCOT Sep 2020target 2028
Neal Solar
Solar · SolarGen Resources LLC
252 MWWithdrawn / abandoned Wharton, TXERCOT Nov 2020target 2023
BRP Batura BESS
Battery storage · BRP Batura BESS LLC
252 MWWithdrawn / abandoned ERCOT Dec 2020target 2025
Langer Solar
Solar · Langer Solar LLC
250 MWWithdrawn / abandoned Bosque, TXERCOT Jun 2020target 2027
BRP Pular BESS
Battery storage · BRP Pular BESS LLC
233 MWWithdrawn / abandoned ERCOT Sep 2020target 2027
Cottage Meadow Storage
Other · KCE TX 18, LLC
209 MWWithdrawn / abandoned Cameron, TXERCOT Jan 2020target 2021
Neptune Solar
Solar · Matagorda Solar LLC
206 MWWithdrawn / abandoned ERCOT Apr 2020target 2026
Egret Hill Storage
Other · Coyote Crossing LLC
206 MWWithdrawn / abandoned Hunt, TXERCOT Sep 2020target 2021
Galactic Solar
Solar · UKA North America, LLC
205 MWWithdrawn / abandoned ERCOT Dec 2020target 2027
Thunderbird Solar SLF
Solar · Thunderbird Solar, LLC
204 MWWithdrawn / abandoned Milam, TXERCOT Dec 2020target 2024
Flagtail Batt
Other · Flagtail LLC
204 MWWithdrawn / abandoned Grimes, TXERCOT Apr 2020target 2022
BRP Lyra BESS
Other · BRP Lyra BESS LLC
203 MWWithdrawn / abandoned Pecos, TXERCOT Jun 2020target 2022
Corbin Grid BESS
Other · Corbin Grid, LLC
203 MWWithdrawn / abandoned Fort Bend, TXERCOT Aug 2020target 2026
Wekiva Grid
Battery storage · Wekiva Grid, LLC
203 MWWithdrawn / abandoned Titus, TXERCOT Aug 2020target 2024
Sibyl Energy Storage
Other · WattBridge Energy, LLC
202 MWWithdrawn / abandoned Fort Bend, TXERCOT Dec 2020target 2024
Topaz Energy Storage
Other · WattBridge Energy, LLC
202 MWWithdrawn / abandoned Galveston, TXERCOT Dec 2020target 2025
Clybourn Solar
Solar · Leeward Renewable Energy Development, LLC
202 MWWithdrawn / abandoned Matagorda, TXERCOT May 2020target 2022
Milwaukee Solar
Solar · Leeward Renewable Energy Development, LLC
202 MWWithdrawn / abandoned Matagorda, TXERCOT Nov 2020target 2022
BRP Kailas BESS
Battery storage · BRP Kailas BESS LLC
201 MWWithdrawn / abandoned ERCOT Dec 2020target 2027
Raoul Solar
Solar · Leeward Renewable Energy Development, LLC
201 MWWithdrawn / abandoned Fort Bend, TXERCOT Oct 2020target 2023
Elston Solar
Solar · Leeward Renewable Energy Development, LLC
201 MWWithdrawn / abandoned Matagorda, TXERCOT May 2020target 2023
Amsterdam Storage
Battery storage · Cottonwood Bayou II Storage, LLC
201 MWWithdrawn / abandoned ERCOT Oct 2020target 2026
BRP Bonete BESS
Battery storage · BRP Bonete BESS LLC
201 MWWithdrawn / abandoned ERCOT Dec 2020target 2027
Painted Horse Solar
Solar · RWE Solar Development, LLC
201 MWWithdrawn / abandoned ERCOT Feb 2020target 2025
Girasol
Solar · OCI SOLAR POWER
200 MWWithdrawn / abandoned Zavala, TXERCOT May 2020target 2022
Bonita Creek Solar
Solar · Invenergy Solar Development North America LLC
200 MWWithdrawn / abandoned Atascosa, TXERCOT Dec 2020target 2026
Delilah Solar 3
Solar
200 MWWithdrawn / abandoned Lamar, TXERCOT Jun 2020
Brangus Storage
Other · 245CK 8me LLC
200 MWWithdrawn / abandoned Kinney, TXERCOT Jan 2020target 2023
Seaside Solar
Solar · Seadrift Solar
200 MWWithdrawn / abandoned Calhoun, TXERCOT Dec 2020target 2024
Hopkins BESS
Other · Hopkins Energy, LLC
188 MWWithdrawn / abandoned Hopkins, TXERCOT Nov 2020target 2023
Arana Creek Batt
Battery storage · Arana Creek LLC
154 MWWithdrawn / abandoned ERCOT Jun 2020target 2026
Evergreen Solar
Solar · Bucks Bayou LLC
150 MWWithdrawn / abandoned Matagorda, TXERCOT Dec 2020target 2025
Nolan Solar
Solar · Tenaska Solar XVII, LLC
150 MWWithdrawn / abandoned Nolan, TXERCOT Jan 2020target 2023
SkySealy
Gas · Sky Global Power Two, LLC
149 MWWithdrawn / abandoned Austin, TXERCOT Apr 2020target 2025
Ponil Solar
Solar · Innovative Solar 377, LLC
145 MWWithdrawn / abandoned Childress, TXERCOT Feb 2020target 2025
Desert Vine Solar
Solar · Desert Vine Solar LLC
121 MWWithdrawn / abandoned ERCOT May 2020target 2026
Barrel Summit Storage
Other · KCE TX 14, LLC
117 MWWithdrawn / abandoned Ellis, TXERCOT Jun 2020target 2022
Equinox Storage
Battery storage · Invenergy Storage Development LLC
103 MWWithdrawn / abandoned ERCOT Jun 2020target 2029
Cone Mountain Batt
Other · Ramsay Draw LLC
103 MWWithdrawn / abandoned Brewster, TXERCOT Sep 2020target 2021
Estonian 2 Solar
Solar · 249RD 8ME
102 MWWithdrawn / abandoned ERCOT Aug 2020target 2022
Vorsavio Grid BESS
Other · Vorsavio Grid, LLC
101 MWWithdrawn / abandoned Webb, TXERCOT Oct 2020target 2024
Beachwood Energy Storage (Mark One BESS)
Other · Mark One Energy Storage, LLC
101 MWWithdrawn / abandoned Brazoria, TXERCOT Dec 2020target 2024
Delilah Solar 4
Solar
90.0 MWWithdrawn / abandoned Lamar, TXERCOT Jul 2020
Cannon Solar SLF
Solar · Cannon Solar, LLC
80.0 MWWithdrawn / abandoned ERCOT Sep 2020target 2027
BRP Galan BESS
Battery storage · BRP Galan BESS LLC
76.0 MWWithdrawn / abandoned ERCOT Aug 2020target 2027
SBranch Expansion Solar
Solar · CG Wharton County LLC
76.0 MWWithdrawn / abandoned Wharton, TXERCOT Oct 2020target 2022
Page 1 of 2

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines · Planned power plants (EIA)