United States βΊ Grid βΊ Interconnection queues βΊ Texas
GAS Β· ERCOTSkySealy
SkySealy is a 149 MW gas request withdrawn in the ERCOT interconnection queue, in Austin County, Texas.
Queue statusWithdrawn / abandoned
- PlanningQueued Apr 2020 (completed)
- Withdrawn / abandonedJun 2024 (project stopped here)
- ConsentedFeb 2023 (not reached)
- Construction (not reached)
- Operating (not reached)
- Closed (not reached)
Request details
- Queue ID
- 21INR0500
- Grid region
- ERCOT (Texas)
- Developer
- Sky Global Power Two, LLC
- Connection point (POI)
- tap 138kV 44700 Gebhardt - 44740 Wallis circuit 65
- Location
- Austin County, Texas
- Technology
- Gas: 149 MW
- Total requested
- 149 MW
- Study phase
- IA
- Queue status
- Withdrawn
- Entered queue
- 30 April 2020
- Agreement signed
- 3 February 2023
- Proposed online date
- June 2025
- Withdrawn
- June 2024
Location
Marker shows the centre of Austin County; the queue data does not give exact sites.
Other requests in Austin County
- EmberYorkGas Β· 900 MW Β· agreement signed
- Sky Global West HoustonGas Β· 325 MW Β· agreement signed
- Symphony BESSBattery storage Β· 612 MW Β· in study
- Sunrose Renewable Energy Solar SLFSolar + storage Β· 310 MW Β· in study
- Homestead Power (TEF-Due Diligence)Gas Β· 260 MW Β· in study
- Saddlehorn Energy StorageBattery storage Β· 257 MW Β· in study
- Parula Energy CenterBattery storage Β· 251 MW Β· in study
- Prost ESSBattery storage Β· 203 MW Β· in study
- BremRaek BESSBattery storage Β· 201 MW Β· in study
- Pamplona StorageSolar + storage Β· 154 MW Β· in study
- Pamplona SolarSolar + storage Β· 42.4 MW Β· in study
- ELTEX Power StationGas Β· 488 MW Β· withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem