Sibyl Energy Storage is a 202 MW other request withdrawn in the ERCOT interconnection queue, in Fort Bend County, Texas.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Dec 2020 (completed)
  2. Withdrawn / abandonedJan 2024 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
22INR0449
Grid region
ERCOT (Texas)
Developer
WattBridge Energy, LLC
Connection point (POI)
Tap 138kV 43261 Southwyck - 44552 Telview
Location
Fort Bend County, Texas
Technology
Other: 202 MW
Total requested
202 MW
Study phase
FIS
Queue status
Withdrawn
Entered queue
2 December 2020
Proposed online date
November 2024
Withdrawn
January 2024

Location

Marker shows the centre of Fort Bend County; the queue data does not give exact sites.

Power plants in Texas Β· Transmission lines in Texas

Other requests in Fort Bend County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem