United States βΊ Grid βΊ Interconnection queues βΊ Texas
OTHER Β· ERCOTBarrel Summit Storage
Barrel Summit Storage is a 117 MW other request withdrawn in the ERCOT interconnection queue, in Ellis County, Texas.
Queue statusWithdrawn / abandoned
- PlanningQueued Jun 2020 (completed)
- Withdrawn / abandonedApr 2021 (project stopped here)
- Consented (not reached)
- Construction (not reached)
- Operating (not reached)
- Closed (not reached)
Request details
- Queue ID
- 22INR0348
- Grid region
- ERCOT (Texas)
- Developer
- KCE TX 14, LLC
- Connection point (POI)
- 221 Trumbull 138kV
- Location
- Ellis County, Texas
- Technology
- Other: 117 MW
- Total requested
- 117 MW
- Study phase
- FIS
- Queue status
- Withdrawn
- Entered queue
- 8 June 2020
- Proposed online date
- December 2022
- Withdrawn
- April 2021
Location
Marker shows the centre of Ellis County; the queue data does not give exact sites.
Other requests in Ellis County
- Oystercatcher SolarSolar Β· 222 MW Β· agreement signed
- Cumulus Grid BESSBattery storage Β· 211 MW Β· agreement signed
- Sol Marina Energy CenterSolar + storage Β· 175 MW Β· agreement signed
- Sol Marina Energy Center BESSSolar + storage Β· 57.2 MW Β· agreement signed
- Kickstart Energy Storage VIBattery storage Β· 1,026 MW Β· in study
- Kickstart Energy Storage VBattery storage Β· 999 MW Β· in study
- Two Step SolarSolar Β· 405 MW Β· in study
- Galaxy Solar 2Solar Β· 302 MW Β· in study
- Galaxy Storage 2Battery storage Β· 202 MW Β· in study
- Galaxy StorageSolar + storage Β· 155 MW Β· in study
- Bluebonnet Trail SolarSolar Β· 151 MW Β· in study
- Galaxy SolarSolar + storage Β· 148 MW Β· in study
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem