Two Step Solar

Two Step Solar is a 405 MW solar request in interconnection study in the ERCOT interconnection queue, in Ellis County, Texas.

Queue statusIn planning
  1. PlanningQueued Dec 2025 (current stage)
  2. Consented (not yet reached)
  3. Construction (not yet reached)
  4. OperatingTarget Aug 2029 (not yet reached)
  5. Closed (not yet reached)

Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.

Request details

Queue ID
29INR0196
Grid region
ERCOT (Texas)
Developer
Two Step Solar, LLC
Connection point (POI)
NAVARRO to VENUS_N5
Location
Ellis County, Texas
Technology
Solar: 405 MW
Total requested
405 MW
Study phase
SS Started, FIS Started, No IA
Queue status
Active
Entered queue
17 December 2025
Proposed online date
August 2029

Location

Marker shows the centre of Ellis County; the queue data does not give exact sites.

Power plants in Texas · Transmission lines in Texas

Other requests in Ellis County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem