Thunderbird Solar SLF

Thunderbird Solar SLF is a 204 MW solar request withdrawn in the ERCOT interconnection queue, in Milam County, Texas.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Dec 2020 (completed)
  2. Withdrawn / abandonedNov 2021 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
23INR0148
Grid region
ERCOT (Texas)
Developer
Thunderbird Solar, LLC
Connection point (POI)
tap 138kV 3684 Minerva - 64 Milano
Location
Milam County, Texas
Technology
Solar: 204 MW
Total requested
204 MW
Study phase
FIS
Queue status
Withdrawn
Entered queue
22 December 2020
Proposed online date
April 2024
Withdrawn
November 2021

Location

Marker shows the centre of Milam County; the queue data does not give exact sites.

Power plants in Texas Β· Transmission lines in Texas

Other requests in Milam County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem