πŸ”Œ EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more β†’ Skip to main content

United States β€Ί Grid β€Ί Interconnection queues β€Ί Texas

SOLAR Β· ERCOT

Delilah Solar 3

Delilah Solar 3 is a 200 MW solar request withdrawn in the ERCOT interconnection queue, in Lamar County, Texas.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Jun 2020 (completed)
  2. Withdrawn / abandonedMay 2023 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
23INR0042
Grid region
ERCOT (Texas)
Location
Lamar County, Texas
Technology
Solar: 200 MW
Total requested
200 MW
Queue status
Withdrawn
Entered queue
2 June 2020
Withdrawn
May 2023

Location

Marker shows the centre of Lamar County; the queue data does not give exact sites.

Power plants in Texas Β· Transmission lines in Texas

Other requests in Lamar County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem