United States βΊ Grid βΊ Interconnection queues βΊ Texas
SOLAR Β· ERCOTDelilah Solar 3
Delilah Solar 3 is a 200 MW solar request withdrawn in the ERCOT interconnection queue, in Lamar County, Texas.
Queue statusWithdrawn / abandoned
- PlanningQueued Jun 2020 (completed)
- Withdrawn / abandonedMay 2023 (project stopped here)
- Consented (not reached)
- Construction (not reached)
- Operating (not reached)
- Closed (not reached)
Request details
- Queue ID
- 23INR0042
- Grid region
- ERCOT (Texas)
- Location
- Lamar County, Texas
- Technology
- Solar: 200 MW
- Total requested
- 200 MW
- Queue status
- Withdrawn
- Entered queue
- 2 June 2020
- Withdrawn
- May 2023
Location
Marker shows the centre of Lamar County; the queue data does not give exact sites.
Other requests in Lamar County
- Baker Branch SolarSolar Β· 469 MW Β· agreement signed
- Bug Tussle Wind ProjectOnshore wind Β· 397 MW Β· agreement signed
- Rowdy Creek SolarSolar + storage Β· 352 MW Β· agreement signed
- Delilah Solar 2Solar Β· 318 MW Β· agreement signed
- Delilah Solar 1Solar Β· 300 MW Β· agreement signed
- Samson Solar 3Solar Β· 250 MW Β· agreement signed
- Samson Solar 1Solar Β· 250 MW Β· agreement signed
- Star Dairy StorageSolar + storage Β· 205 MW Β· agreement signed
- Samson Solar 2Solar Β· 203 MW Β· agreement signed
- Echols Grove, LLCSolar Β· 201 MW Β· agreement signed
- Rowdy Creek BESSSolar + storage Β· 176 MW Β· agreement signed
- MRG Goody SolarSolar + storage Β· 171 MW Β· agreement signed
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem