ONSHORE WIND · ERCOT

Bug Tussle Wind Project

Bug Tussle Wind Project is a 397 MW onshore wind request with a signed interconnection agreement in the ERCOT interconnection queue, in Lamar County, Texas.

Queue statusConsented
  1. PlanningQueued Jan 2022 (completed)
  2. ConsentedJul 2024 (current stage)
  3. Construction (not yet reached)
  4. OperatingTarget Aug 2027 (not yet reached)
  5. Closed (not yet reached)

Request details

Queue ID
23INR0441
Grid region
ERCOT (Texas)
Developer
Bug Tussle Wind, LLC
Connection point (POI)
Tap 1729 Valley South and 1692 Paris
Location
Lamar County, Texas
Technology
Wind: 397 MW
Total requested
397 MW
Study phase
SS Completed, FIS Started, IA
Queue status
Active
Entered queue
13 January 2022
Agreement signed
10 July 2024
Proposed online date
August 2027

Location

Marker shows the centre of Lamar County; the queue data does not give exact sites.

Power plants in Texas · Transmission lines in Texas

Other requests in Lamar County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem