MRG Goody Solar

MRG Goody Solar is a 171 MW solar + storage request with a signed interconnection agreement in the ERCOT interconnection queue, in Lamar County, Texas.

Queue statusConsented
  1. PlanningQueued Mar 2021 (completed)
  2. ConsentedNov 2023 (current stage)
  3. Construction (not yet reached)
  4. OperatingTarget Mar 2026 (not yet reached)
  5. Closed (not yet reached)

Request details

Queue ID
23INR0225
Grid region
ERCOT (Texas)
Developer
MRG GOODY SOLAR PROJECT, LLC
Connection point (POI)
Tap 138 kV Toco Switch (#1700) – Paris Switch (#1693)
Location
Lamar County, Texas
Technology
Solar: 171 MW · Battery
Total requested
171 MW
Study phase
SS Completed, FIS Completed, IA
Queue status
Active
Entered queue
16 March 2021
Agreement signed
7 November 2023
Proposed online date
March 2026

Location

Marker shows the centre of Lamar County; the queue data does not give exact sites.

Power plants in Texas · Transmission lines in Texas

Other requests in Lamar County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem