United States › Grid › Interconnection queues › Texas
SOLAR + STORAGE · ERCOTMRG Goody Solar
MRG Goody Solar is a 171 MW solar + storage request with a signed interconnection agreement in the ERCOT interconnection queue, in Lamar County, Texas.
Queue statusConsented
- PlanningQueued Mar 2021 (completed)
- ConsentedNov 2023 (current stage)
- Construction (not yet reached)
- OperatingTarget Mar 2026 (not yet reached)
- Closed (not yet reached)
Request details
- Queue ID
- 23INR0225
- Grid region
- ERCOT (Texas)
- Developer
- MRG GOODY SOLAR PROJECT, LLC
- Connection point (POI)
- Tap 138 kV Toco Switch (#1700) – Paris Switch (#1693)
- Location
- Lamar County, Texas
- Technology
- Solar: 171 MW · Battery
- Total requested
- 171 MW
- Study phase
- SS Completed, FIS Completed, IA
- Queue status
- Active
- Entered queue
- 16 March 2021
- Agreement signed
- 7 November 2023
- Proposed online date
- March 2026
Location
Marker shows the centre of Lamar County; the queue data does not give exact sites.
Other requests in Lamar County
- Baker Branch SolarSolar · 469 MW · agreement signed
- Bug Tussle Wind ProjectOnshore wind · 397 MW · agreement signed
- Rowdy Creek SolarSolar + storage · 352 MW · agreement signed
- Delilah Solar 2Solar · 318 MW · agreement signed
- Delilah Solar 1Solar · 300 MW · agreement signed
- Samson Solar 3Solar · 250 MW · agreement signed
- Samson Solar 1Solar · 250 MW · agreement signed
- Star Dairy StorageSolar + storage · 205 MW · agreement signed
- Samson Solar 2Solar · 203 MW · agreement signed
- Echols Grove, LLCSolar · 201 MW · agreement signed
- Rowdy Creek BESSSolar + storage · 176 MW · agreement signed
- Star Dairy SolarSolar + storage · 126 MW · agreement signed
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem