πŸ”Œ EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more β†’ Skip to main content

United States β€Ί Grid β€Ί Interconnection queues

SOLAR Β· ERCOT

Estonian 2 Solar

Estonian 2 Solar is a 102 MW solar request withdrawn in the ERCOT interconnection queue.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Aug 2020 (completed)
  2. Withdrawn / abandonedAug 2020 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
22INR0373
Grid region
ERCOT (Texas)
Developer
249RD 8ME
Connection point (POI)
tap 138kV 1801 Paris Pump Tap β€šΓ„Γ¬ 17011 LKCRK_P8
Technology
Solar: 102 MW
Total requested
102 MW
Study phase
FIS & SS Incomplete
Queue status
Withdrawn
Entered queue
4 August 2020
Proposed online date
December 2022
Withdrawn
August 2020

Location

No county location in the queue data.

Power plants in Β· Transmission lines in

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem