πŸ”Œ EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more β†’ Skip to main content

United States β€Ί Grid β€Ί Interconnection queues β€Ί Texas

SOLAR Β· ERCOT

Langer Solar

Langer Solar is a 250 MW solar request withdrawn in the ERCOT interconnection queue, in Bosque County, Texas.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Jun 2020 (completed)
  2. Withdrawn / abandonedDec 2025 (project stopped here)
  3. ConsentedAug 2023 (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
23INR0030
Grid region
ERCOT (Texas)
Developer
Langer Solar LLC
Connection point (POI)
tap 345kV 68040 Kopperl - 68091 Navarro
Location
Bosque County, Texas
Technology
Solar: 250 MW
Total requested
250 MW
Study phase
IA and FIS Pending
Queue status
Withdrawn
Entered queue
2 June 2020
Agreement signed
31 August 2023
Proposed online date
March 2027
Withdrawn
December 2025

Location

Marker shows the centre of Bosque County; the queue data does not give exact sites.

Power plants in Texas Β· Transmission lines in Texas

Other requests in Bosque County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem