United States › Grid › Interconnection queues › Texas

SOLAR · ERCOT

Symank Solar

Symank Solar is a 66.6 MW solar request in interconnection study in the ERCOT interconnection queue, in Bosque County, Texas.

Queue statusIn planning
  1. PlanningQueued Nov 2024 (current stage)
  2. Consented (not yet reached)
  3. Construction (not yet reached)
  4. OperatingTarget Dec 2027 (not yet reached)
  5. Closed (not yet reached)

Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.

Request details

Queue ID
27INR0298
Grid region
ERCOT (Texas)
Developer
BT Symank Solar, LLC
Connection point (POI)
Tap 69 kV 37470 TNOLSEN - 37520 TNSYCAMORE
Location
Bosque County, Texas
Technology
Solar: 66.6 MW
Total requested
66.6 MW
Study phase
SS Completed, FIS Started, No IA
Queue status
Active
Entered queue
19 November 2024
Proposed online date
December 2027

Location

Marker shows the centre of Bosque County; the queue data does not give exact sites.

Power plants in Texas · Transmission lines in Texas

Other requests in Bosque County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem