United States βΊ Grid βΊ Interconnection queues βΊ Texas
SOLAR Β· ERCOTDileo Solar
Dileo Solar is a 71.4 MW solar request built and operating in the ERCOT interconnection queue, in Bosque County, Texas.
Request details
- Queue ID
- 22INR0359
- Grid region
- ERCOT (Texas)
- Developer
- Elawan Dileo Solar LLC
- Connection point (POI)
- tap 69kV 37470 TN Olsen - 37420 TN Lake Whitney
- Location
- Bosque County, Texas
- Technology
- Solar: 71.4 MW
- Total requested
- 71.4 MW
- Study phase
- IA
- Queue status
- Operational
- Entered queue
- 18 June 2020
- Agreement signed
- 17 September 2021
- Proposed online date
- November 2023
- Came online
- November 2023
Location
Marker shows the centre of Bosque County; the queue data does not give exact sites.
Other requests in Bosque County
- Hickerson SolarSolar + storage Β· 311 MW Β· agreement signed
- Woodland Energy StorageBattery storage Β· 208 MW Β· in study
- BRP Pollux BESSBattery storage Β· 163 MW Β· in study
- Solheim SolarSolar Β· 109 MW Β· in study
- Symank SolarSolar Β· 66.6 MW Β· in study
- Meridian BESSBattery storage Β· 31.2 MW Β· in study
- Sultan SolarSolar Β· 206 MW Β· suspended
- Sultan BESSBattery storage Β· 204 MW Β· suspended
- Owens SolarSolar Β· 204 MW Β· suspended
- Rueter SolarSolar Β· 200 MW Β· suspended
- Angus SolarSolar Β· 113 MW Β· suspended
- Angus StorageBattery storage Β· 63.0 MW Β· suspended
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem