SOLAR Β· ERCOT

Milwaukee Solar

Milwaukee Solar is a 202 MW solar request withdrawn in the ERCOT interconnection queue, in Matagorda County, Texas.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Nov 2020 (completed)
  2. Withdrawn / abandonedJan 2022 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
22INR0441
Grid region
ERCOT (Texas)
Developer
Leeward Renewable Energy Development, LLC
Connection point (POI)
tap 138kV 8608 Pavlov to 8127 South Lane City
Location
Matagorda County, Texas
Technology
Solar: 202 MW
Total requested
202 MW
Study phase
FIS
Queue status
Withdrawn
Entered queue
4 November 2020
Proposed online date
December 2022
Withdrawn
January 2022

Location

Marker shows the centre of Matagorda County; the queue data does not give exact sites.

Power plants in Texas Β· Transmission lines in Texas

Other requests in Matagorda County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem