United States › Grid › Interconnection queues › Texas
SOLAR · ERCOTBluefox Solar 1
Bluefox Solar 1 is a 403 MW solar request in interconnection study in the ERCOT interconnection queue, in Matagorda County, Texas.
Queue statusIn planning
- PlanningQueued Mar 2024 (current stage)
- Consented (not yet reached)
- Construction (not yet reached)
- OperatingTarget May 2029 (not yet reached)
- Closed (not yet reached)
Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.
Request details
- Queue ID
- 27INR0141
- Grid region
- ERCOT (Texas)
- Developer
- Industrial November Project LLC
- Connection point (POI)
- #8754 Zoisite 345kV
- Location
- Matagorda County, Texas
- Technology
- Solar: 403 MW
- Total requested
- 403 MW
- Study phase
- SS Completed, FIS Started, No IA
- Queue status
- Active
- Entered queue
- 22 March 2024
- Proposed online date
- May 2029
Location
Marker shows the centre of Matagorda County; the queue data does not give exact sites.
Other requests in Matagorda County
- Duffy SolarSolar + storage · 503 MW · agreement signed
- Lavaca Bay SolarSolar · 244 MW · agreement signed
- Peyton Creek Wind IIOnshore wind · 241 MW · agreement signed
- Duffy BESSSolar + storage · 241 MW · agreement signed
- Eldora BESSSolar + storage · 201 MW · agreement signed
- Eldora SolarSolar + storage · 201 MW · agreement signed
- City Breeze BESSBattery storage · 143 MW · agreement signed
- Matagorda SolarSolar · 101 MW · agreement signed
- Isaac SolarSolar · 50.7 MW · agreement signed
- Bluefox Solar 2Solar · 402 MW · in study
- Juanita Creek BESSBattery storage · 304 MW · in study
- Charolais SolarSolar + storage · 262 MW · in study