United States › Grid › Interconnection queues › Texas

SOLAR · ERCOT

Isaac Solar

Isaac Solar is a 50.7 MW solar request with a signed interconnection agreement in the ERCOT interconnection queue, in Matagorda County, Texas.

Queue statusConsented
  1. PlanningQueued Nov 2022 (completed)
  2. ConsentedOct 2023 (current stage)
  3. Construction (not yet reached)
  4. OperatingTarget Dec 2026 (not yet reached)
  5. Closed (not yet reached)

Request details

Queue ID
25INR0232
Grid region
ERCOT (Texas)
Developer
Industrial Bravo Project LLC
Connection point (POI)
8114 Conoco 138kV
Location
Matagorda County, Texas
Technology
Solar: 50.7 MW
Total requested
50.7 MW
Study phase
SS Completed, FIS Completed, IA
Queue status
Active
Entered queue
7 November 2022
Agreement signed
18 October 2023
Proposed online date
December 2026

Location

Marker shows the centre of Matagorda County; the queue data does not give exact sites.

Power plants in Texas · Transmission lines in Texas

Other requests in Matagorda County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem