United States › Grid › Interconnection queues › Texas

SOLAR + STORAGE · ERCOT

Eldora Solar

Eldora Solar is a 201 MW solar + storage request with a signed interconnection agreement in the ERCOT interconnection queue, in Matagorda County, Texas.

Queue statusConsented
  1. PlanningQueued Jun 2022 (completed)
  2. ConsentedNov 2023 (current stage)
  3. Construction (not yet reached)
  4. OperatingTarget Jul 2028 (not yet reached)
  5. Closed (not yet reached)

Request details

Queue ID
24INR0337
Grid region
ERCOT (Texas)
Developer
Eldora Energy LLC
Connection point (POI)
Tap 345 kV 5915 South Texas Project – 44200 Hillje Ckt 1
Location
Matagorda County, Texas
Technology
Solar: 201 MW · Battery
Total requested
201 MW
Study phase
SS Completed, FIS Started, IA
Queue status
Active
Entered queue
10 June 2022
Agreement signed
15 November 2023
Proposed online date
July 2028

Location

Marker shows the centre of Matagorda County; the queue data does not give exact sites.

Power plants in Texas · Transmission lines in Texas

Other requests in Matagorda County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem