πŸ”Œ EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more β†’ Skip to main content

United States β€Ί Grid β€Ί Interconnection queues

BATTERY STORAGE Β· ERCOT

BRP Pobeda BESS

BRP Pobeda BESS is a 301 MW battery storage request withdrawn in the ERCOT interconnection queue.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Nov 2020 (completed)
  2. Withdrawn / abandoned (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
23INR0115
Grid region
ERCOT (Texas)
Developer
BRP Pobeda BESS LLC
Connection point (POI)
44645 Singleton 345kV
Technology
Battery: 301 MW
Total requested
301 MW
Study phase
FIS
Queue status
Withdrawn
Entered queue
18 November 2020
Proposed online date
December 2028

Location

No county location in the queue data.

Power plants in Β· Transmission lines in

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem