United States › Grid › Interconnection queues › Texas

OCTARY USA · INTERCONNECTION QUEUES

Interconnection queue in Texas — page 6

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown2,094476.4 GW
Active in queue476.4 GW2,094 requests
Agreement signed124.6 GW606 requests
Withdrawn917184.2 GW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

2,094 requests · page 6 of 42
ProjectCapacityStatusLocationRegionQueuedOnline
Infinium Solar
Solar · Jackalope Flats Solar, LLC
402 MWIn study Howard, TXERCOT Aug 2024target 2029
Bottom Grass Solar II
Solar + storage · Flint Rock Solar Project, LLC
402 MWIn study Colorado, TXERCOT Nov 2022target 2028
Corruscant BESS
Battery storage · AEU Battery Project III LLC
402 MWIn study Dickens, TXERCOT Feb 2024target 2027
Dorado Solar
Solar · Enbridge Solar (Sequoia I), LLC
401 MWAgreement signed Callahan, TXERCOT Jan 2020target 2026
Onshore wind project GEN-2024-109, Bailey County
Onshore wind
401 MWIn study Bailey, TXSPP Mar 2025target 2031
Solar + storage project GEN-2021-090, Yoakum County
Solar + storage
400 MWIn study Yoakum, TXSPP Apr 2021target 2028
Gridline Solar
Solar · Big Lake Ranch LLC
400 MWIn study Crockett, TXERCOT Aug 2025target 2029
Vaquero 1 Wind
Onshore wind · Enerverse
400 MWIn study Zapata, TXERCOT Apr 2016target 2027
Exergy Energy West Texas Natural Gas Reciprocating Power I
Gas · August Partners LLC
400 MWIn study Reeves, TXERCOT Jul 2025target 2027
Biggs Solar
Solar + storage · Biggs Solar Farm, LLC
400 MWIn study Mcculloch, TXERCOT Jul 2024target 2028
Springfield Solar
Solar · BOULEVARD ASSOCIATES, LLC
400 MWIn study Pecos, TXERCOT Sep 2025target 2028
Boling Generation (TEF-Due Diligience)
Gas · Boling Generation
400 MWIn study Wharton, TXERCOT Dec 2023target 2027
Hanson Solar
Solar · Hanson Solar, LLC
399 MWAgreement signed Coleman, TXERCOT Oct 2020target 2027
Charger Solar
Solar · AP Solar 4, LLC
397 MWAgreement signed Refugio, TXERCOT Jun 2020target 2026
Bug Tussle Wind Project
Onshore wind · Bug Tussle Wind, LLC
397 MWAgreement signed Lamar, TXERCOT Jan 2022target 2027
Solar project ERAS-2025-028, Hockley County
Solar
384 MWIn study Hockley, TXSPP Oct 2025target 2030
Moon Chapel Wind
Onshore wind · Orsted Onshore Development North America, LLC
379 MWIn study Tom Green, TXERCOT Feb 2025target 2028
Paint Rock Wind
Onshore wind · Orsted Onshore Development North America, LLC
379 MWIn study Concho, TXERCOT Jan 2024target 2028
Panhandle Flagship Storage
Solar + storage · Panhandle Solar Group Operating Company LLC
372 MWAgreement signed Carson, TXERCOT Mar 2023target 2027
Kilby1 Part 1 Small Block Simple Cycle
Gas · Energy Forge One LLC
371 MWIn study Reeves, TXERCOT Oct 2025target 2027
Earthwise Solar
Solar · Quanah Solar 2
371 MWIn study Hardeman, TXERCOT Mar 2022target 2026
Skyrider Wind
Onshore wind · NextEra Energy Interconnection Holdings, LLC
370 MWIn study Pecos, TXERCOT Nov 2024target 2028
Viento Bravo Wind
Onshore wind · Webb Wind, LLC
367 MWIn study Jim Hogg, TXERCOT Oct 2025target 2028
Space City Solar
Solar · Apollo Solar Ranch, LLC
366 MWAgreement signed Wharton, TXERCOT Nov 2019target 2027
Scott Crossing Solar SLF
Solar + storage · FRESH AIR ENERGY II, LLC
364 MWIn study Haskell, TXERCOT Mar 2023target 2027
Aldrin 345 BESS
Battery storage · Aldrin Energy Storage LLC
362 MWAgreement signed Brazoria, TXERCOT May 2023target 2027
Channing Wind
Onshore wind
361 MWPaused / redesign Oldham, TXERCOT Dec 2023target 2028
Wildflower Storage
Battery storage · Wildflower Storage LLC
359 MWIn study Navarro, TXERCOT Jun 2025target 2028
Tetris Solar
Solar · NextEra Energy Interconnection Holdings LLC
359 MWIn study Zapata, TXERCOT Jul 2023target 2029
Tetris Solar (Alternative POI)
Solar
359 MWPaused / redesign Zapata, TXERCOT Jul 2023target 2028
Twinwood Solar 1
Solar · Twinwood PV1, LLC
358 MWIn study Waller, TXERCOT Mar 2024target 2027
Green Ocelot Solar
Solar + storage · Ocelot Solar LLC
357 MWIn study Kenedy, TXERCOT Jan 2025target 2028
Tormes Solar
Solar · BDPU SOLAR TORMES LLC
357 MWAgreement signed Navarro, TXERCOT Oct 2020target 2027
Funston Solar (AEP POI)
Solar
355 MWPaused / redesign Jones, TXERCOT Sep 2023target 2028
Max 4 Wind
Onshore wind · Lake Creek Wind, LLC
353 MWIn study Haskell, TXERCOT Jul 2025target 2028
Longview Wind
Onshore wind · Longview Wind, LLC
353 MWAgreement signed Dawson, TXERCOT Sep 2025target 2028
Onshore wind project GEN-2020-067, Terry County
Onshore wind
353 MWIn study Terry, TXSPP Apr 2020target 2026
Chillingham Solar
Solar · Chillingham Solar LLC
352 MWAgreement signed Bell, TXERCOT Aug 2020target 2026
Lucy Solar
Solar · Concho County Solar 1 LLC
352 MWAgreement signed Concho, TXERCOT Jun 2023target 2027
Sombrero Solar
Solar · Aurora Solar LLC
352 MWIn study Schleicher, TXERCOT Mar 2022target 2028
West Munday Wind
Onshore wind · Lake Creek Wind, LLC
352 MWAgreement signed Knox, TXERCOT Nov 2024target 2028
Rowdy Creek Solar
Solar + storage · Rowdy Creek Solar LLC
352 MWAgreement signed Lamar, TXERCOT Jan 2022target 2027
Cottonwood Bayou Solar
Solar · Cottonwood Bayou Solar, LLC
351 MWAgreement signed Brazoria, TXERCOT Sep 2017target 2026
Fighting Jays Solar
Solar · AP Solar Holdings, LLC
351 MWAgreement signed Fort Bend, TXERCOT Mar 2019target 2026
Funston Solar
Solar · Funston Solar LLC
351 MWAgreement signed Jones, TXERCOT Feb 2024target 2027
Brookesmith Storage
Battery storage · Brookesmith Storage LLC
351 MWIn study Brown, TXERCOT Apr 2025target 2029
Solar + storage project GEN-2024-280, Andrews County
Solar + storage
350 MWIn study Andrews, TXSPP Mar 2025target 2029
HyFuels Green Lake Solar
Solar · HyFuels Green Lake Solar LLC
347 MWIn study Victoria, TXERCOT Sep 2022target 2027
Solar project GEN-2024-046, Hansford County
Solar
345 MWIn study Hansford, TXSPP Oct 2024target 2029
Solar project GEN-2024-045, Hansford County
Solar
345 MWIn study Hansford, TXSPP Oct 2024target 2029
Page 6 of 42

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines · Planned power plants (EIA)