🔌 EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more → Skip to main content

United States › Grid › Interconnection queues › Texas

SOLAR · SPP

Solar project ERAS-2025-028, Hockley County

Solar project ERAS-2025-028, Hockley County is a 384 MW solar request in interconnection study in the SPP interconnection queue, in Hockley County, Texas, connecting to SPS.

Queue statusIn planning
  1. PlanningQueued Oct 2025 (current stage)
  2. Consented (not yet reached)
  3. Construction (not yet reached)
  4. OperatingTarget Oct 2030 (not yet reached)
  5. Closed (not yet reached)

Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.

Request details

Queue ID
ERAS-2025-028
Grid region
SPP (Southwest Power Pool)
Utility / transmission owner
SPS
Connection point (POI)
Tuco-Yoakum 345kV Line
Location
Hockley County, Texas
Technology
Solar: 384 MW
Total requested
384 MW
Service type
NRIS and ERIS
Study phase
ERAS
Queue status
Active
Entered queue
2 October 2025
Proposed online date
October 2030

Location

Marker shows the centre of Hockley County; the queue data does not give exact sites.

Power plants in Texas · Transmission lines in Texas

Other requests in Hockley County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem