United States β€Ί Grid β€Ί Interconnection queues β€Ί Texas

SOLAR Β· SPP

Solar project GEN-2021-089, Hockley County

Solar project GEN-2021-089, Hockley County is a 400 MW solar request withdrawn in the SPP interconnection queue, in Hockley County, Texas, connecting to SPS.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Apr 2021 (completed)
  2. Withdrawn / abandonedMay 2022 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
GEN-2021-089
Grid region
SPP (Southwest Power Pool)
Utility / transmission owner
SPS
Connection point (POI)
Tuco-Yoakum-Hobbs 345kV
Location
Hockley County, Texas
Technology
Solar: 400 MW
Total requested
400 MW
Service type
NRIS and ERIS
Study phase
WITHDRAWN
Queue status
Withdrawn
Entered queue
29 April 2021
Proposed online date
December 2026
Withdrawn
May 2022

Location

Marker shows the centre of Hockley County; the queue data does not give exact sites.

Power plants in Texas Β· Transmission lines in Texas

Other requests in Hockley County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem