Tetris Solar (Alternative POI)

Tetris Solar (Alternative POI) is a 359 MW solar request suspended in the ERCOT interconnection queue, in Zapata County, Texas.

Queue statusPaused / redesign
  1. PlanningQueued Jul 2023 (current stage)
  2. Consented (not yet reached)
  3. Construction (not yet reached)
  4. OperatingTarget Jul 2028 (not yet reached)
  5. Closed (not yet reached)

Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.

Request details

Queue ID
28INR0007
Grid region
ERCOT (Texas)
Location
Zapata County, Texas
Technology
Solar: 359 MW
Total requested
359 MW
Queue status
Suspended
Entered queue
9 July 2023
Proposed online date
July 2028

Location

Marker shows the centre of Zapata County; the queue data does not give exact sites.

Power plants in Texas · Transmission lines in Texas

Other requests in Zapata County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem