United States › Grid › Interconnection queues › Texas
SOLAR · ERCOTHanson Solar
Hanson Solar is a 399 MW solar request with a signed interconnection agreement in the ERCOT interconnection queue, in Coleman County, Texas.
Queue statusConsented
- PlanningQueued Oct 2020 (completed)
- ConsentedSep 2023 (current stage)
- Construction (not yet reached)
- OperatingTarget Apr 2027 (not yet reached)
- Closed (not yet reached)
Request details
- Queue ID
- 23INR0086
- Grid region
- ERCOT (Texas)
- Developer
- Hanson Solar, LLC
- Connection point (POI)
- tap 345kV 1444 Brown - 11406 Central Bluff
- Location
- Coleman County, Texas
- Technology
- Solar: 399 MW
- Total requested
- 399 MW
- Study phase
- SS Completed, FIS Started, IA
- Queue status
- Active
- Entered queue
- 23 October 2020
- Agreement signed
- 20 September 2023
- Proposed online date
- April 2027
Location
Marker shows the centre of Coleman County; the queue data does not give exact sites.
Other requests in Coleman County
- Paint Brush PV2Solar · 252 MW · in study
- Paint Brush PV3Solar · 252 MW · in study
- Paint Brush PV4Solar · 252 MW · in study
- Paint Brush PV1Solar · 252 MW · in study
- Invictus Energy StorageBattery storage · 141 MW · in study
- Ulysses Crossing SolarSolar · 405 MW · suspended
- Ulysses Crossing StorageBattery storage · 151 MW · suspended
- Hanson StorageBattery storage · 101 MW · withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem