United States › Grid › Interconnection queues › Texas
SOLAR · ERCOTPaint Brush PV1
Paint Brush PV1 is a 252 MW solar request in interconnection study in the ERCOT interconnection queue, in Coleman County, Texas.
Queue statusIn planning
- PlanningQueued Dec 2025 (current stage)
- Consented (not yet reached)
- Construction (not yet reached)
- OperatingTarget Dec 2028 (not yet reached)
- Closed (not yet reached)
Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.
Request details
- Queue ID
- 28INR0469
- Grid region
- ERCOT (Texas)
- Developer
- Renew Development HoldCo LLC
- Connection point (POI)
- Tap 345 1444 Brown Switch – 60040 Bluff Creek Switch
- Location
- Coleman County, Texas
- Technology
- Solar: 252 MW
- Total requested
- 252 MW
- Study phase
- SS Started, FIS Started, No IA
- Queue status
- Active
- Entered queue
- 2 December 2025
- Proposed online date
- December 2028
Location
Marker shows the centre of Coleman County; the queue data does not give exact sites.
Other requests in Coleman County
- Hanson SolarSolar · 399 MW · agreement signed
- Paint Brush PV2Solar · 252 MW · in study
- Paint Brush PV3Solar · 252 MW · in study
- Paint Brush PV4Solar · 252 MW · in study
- Invictus Energy StorageBattery storage · 141 MW · in study
- Ulysses Crossing SolarSolar · 405 MW · suspended
- Ulysses Crossing StorageBattery storage · 151 MW · suspended
- Hanson StorageBattery storage · 101 MW · withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem