United States › Grid › Interconnection queues › Texas

BATTERY STORAGE · ERCOT

Ulysses Crossing Storage

Ulysses Crossing Storage is a 151 MW battery storage request suspended in the ERCOT interconnection queue, in Coleman County, Texas.

Queue statusPaused / redesign
  1. PlanningQueued Nov 2024 (current stage)
  2. Consented (not yet reached)
  3. Construction (not yet reached)
  4. Operating (not yet reached)
  5. Closed (not yet reached)

Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.

Request details

Queue ID
27INR0415
Grid region
ERCOT (Texas)
Location
Coleman County, Texas
Technology
Battery: 151 MW
Total requested
151 MW
Queue status
Suspended
Entered queue
18 November 2024

Location

Marker shows the centre of Coleman County; the queue data does not give exact sites.

Power plants in Texas · Transmission lines in Texas

Other requests in Coleman County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem