United States › Grid › Interconnection queues › Illinois

OCTARY USA · INTERCONNECTION QUEUES

Interconnection queue in Illinois — page 6

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown42374.6 GW
Active in queue74.6 GW423 requests
Agreement signed7,430 MW51 requests
Withdrawn670115.3 GW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

423 requests · page 6 of 9
ProjectCapacityStatusLocationRegionQueuedOnline
Solar project J1096, Saline County
Solar
150 MWUnder construction Saline, ILMISO Mar 2018target 2024
Solar project J2156, Johnson County
Solar
150 MWIn study Johnson, ILMISO Jun 2022target 2024
Battery storage project J3695, Clark County
Battery storage
150 MWIn study Clark, ILMISO Apr 2024target 2028
Surplus
Battery storage
150 MWIn study St. Clair, ILMISO Jan 2025target 2029
Onshore wind project J750, Morgan County
Onshore wind
150 MWUnder construction Morgan, ILMISO Jun 2017target 2022
Solar project J859, Cass County
Solar
150 MWUnder construction Cass, ILMISO Jun 2017target 2022
Solar project J1744, Cumberland County
Solar
150 MWIn study Cumberland, ILMISO Apr 2022target 2027
Solar project J1651, Logan County
Solar
150 MWIn study Logan, ILMISO Jun 2020target 2023
Onshore wind project J1755, Bureau County
Onshore wind
147 MWIn study Bureau, ILMISO Jun 2020target 2025
Onshore wind project J3754, Iroquois County
Onshore wind
147 MWIn study Iroquois, ILMISO Apr 2024target 2028
Onshore wind project J3755, Iroquois County
Onshore wind
147 MWIn study Iroquois, ILMISO Apr 2024target 2028
Solar project AH2-085, Dekalb County
Solar
145 MWIn study Dekalb, ILPJM Jan 2022target 2026
Solar + storage project J3184, St. Clair County
Solar + storage
145 MWIn study St. Clair, ILMISO Sep 2022target 2027
Onshore wind project J2311, Putnam County
Onshore wind
145 MWIn study Putnam, ILMISO Oct 2024target 2024
Kankakee Solar
Solar · AEUG Kankakee Solar, LLC
144 MWIn study Kankakee, ILPJM Feb 2020target 2021
Battery storage project J3063, Perry County
Battery storage
143 MWIn study Perry, ILMISO Sep 2022target 2026
Solar + storage project J3004, Mason County
Solar + storage
142 MWIn study Mason, ILMISO Sep 2022target 2025
Solar project J3797, Edgar County
Solar
141 MWIn study Edgar, ILMISO Apr 2024target 2028
Solar project J3611, Hamilton County
Solar
140 MWIn study Hamilton, ILMISO Apr 2024target 2026
Solar project J641, Morgan County
Solar
140 MWAgreement signed Morgan, ILMISO May 20162024
Solar project J2972, Adams County
Solar
140 MWIn study Adams, ILMISO Sep 2022target 2026
Onshore wind project J3918, Champaign County
Onshore wind
138 MWIn study Champaign, ILMISO Feb 2025target 2028
Surplus; J33/J734
Other
135 MWIn study Ford, ILMISO May 2023target 2026
Surplus; J734
Other
135 MWIn study Mclean, ILMISO Dec 2022target 2026
Solar + storage project J2648, Champaign County
Solar + storage
135 MWIn study Champaign, ILMISO Sep 2022target 2027
Onshore wind project AI2-390, Mclean County
Onshore wind
134 MWIn study Mclean, ILPJM Mar 2023target 2027
Solar project J2809, Iroquois County
Solar
133 MWIn study Iroquois, ILMISO Sep 2022target 2026
Nuclear project AH1-698, Will County
Nuclear · Constellation Energy Generation, LLC
130 MWIn study Will, ILPJM Apr 2025
Solar + storage project J2738, Rock Island County
Solar + storage
128 MWIn study Rock Island, ILMISO Sep 2022target 2025
Lincoln Capital Land LLC Solar Project
Solar · Lincoln Capital Land LLC
128 MWIn study Sangamon, ILMISO Aug 2025target 2028
Onshore wind project J3820, Hancock County
Onshore wind
127 MWIn study Hancock, ILMISO Apr 2024target 2028
Solar project J1679, Clay County
Solar
125 MWIn study Clay, ILMISO Jun 2020target 2026
Solar project J2384, Shelby County
Solar
125 MWIn study Shelby, ILMISO Sep 2022target 2024
Jackson Generation
Gas
120 MWAgreement signed Will, ILPJM Mar 2018target 2027
Solar project AG2-516, Winnebago County
Solar · Kestrel Solar, LLC
120 MWIn study Winnebago, ILPJM Feb 2025target 2023
Solar + storage project AI1-174, Stephenson County
Solar + storage
118 MWIn study Stephenson, ILPJM Sep 2022target 2028
Buffalo Solar
Solar
116 MWAgreement signed Grundy, ILPJM Mar 2018target 2026
Solar + storage project J2886, Sangamon County
Solar + storage
115 MWIn study Sangamon, ILMISO Sep 2022target 2026
Solar project J3687, Fayette County
Solar
113 MWIn study Fayette, ILMISO Apr 2024target 2027
Solar project J644, Greene County
Solar
110 MWAgreement signed Greene, ILMISO May 20162024
Onshore wind project J3602, Mclean County
Onshore wind
110 MWIn study Mclean, ILMISO Apr 2024target 2028
Solar + storage project AG2-524, Grundy County
Solar + storage · Hog Run Solar, LLC
110 MWIn study Grundy, ILPJM Mar 2025target 2023
Battery storage project AI1-155, Cook County
Battery storage
110 MWIn study Cook, ILPJM Sep 2022target 2027
Battery storage project AH2-015, Lee County
Battery storage
110 MWIn study Lee, ILPJM Oct 2021target 2025
Battery storage project J2551, Putnam County
Battery storage
110 MWIn study Putnam, ILMISO Sep 2022target 2026
Battery storage project AH2-375, Stephenson County
Battery storage
106 MWIn study Stephenson, ILPJM Mar 2022target 2027
Shady Oaks Wind Power Project
Onshore wind
106 MWAgreement signed Lee, ILPJM Mar 2018target 2027
Three Rivers Energy Center
Gas
103 MWAgreement signed Grundy, ILPJM Jul 20172023
Onshore wind project J3456, Tazewell County
Onshore wind
100 MWIn study Tazewell, ILMISO Apr 2024target 2028
Solar project J912, Christian County
Solar
100 MWUnder construction Christian, ILMISO Jun 2017target 2023

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines · Planned power plants (EIA)