🔌 EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more → Skip to main content

United States › Grid › Interconnection queues › Illinois

SOLAR + STORAGE · MISO

Solar + storage project J2738, Rock Island County

Solar + storage project J2738, Rock Island County is a 128 MW solar + storage request in interconnection study in the MISO interconnection queue, in Rock Island County, Illinois, connecting to MIDAMERICAN ENERGY CO..

Queue statusIn planning
  1. PlanningQueued Sep 2022 (current stage)
  2. Consented (not yet reached)
  3. Construction (not yet reached)
  4. OperatingTarget Feb 2025 (not yet reached)
  5. Closed (not yet reached)

Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.

Request details

Queue ID
J2738
Grid region
MISO (Midcontinent)
Utility / transmission owner
MIDAMERICAN ENERGY CO.
Connection point (POI)
SUB 17
Location
Rock Island County, Illinois
Technology
Solar: 128 MW · Battery
Total requested
128 MW
Service type
Network resource (NRIS)
Study phase
Study Phase: DPP 2; Post GIA Status: Not Started
Queue status
Active
Entered queue
15 September 2022
Proposed online date
February 2025

Location

Marker shows the centre of Rock Island County; the queue data does not give exact sites.

Power plants in Illinois · Transmission lines in Illinois

Other requests in Rock Island County