Solar + storage project AG2-517, Rock Island County

Solar + storage project AG2-517, Rock Island County is a 120 MW solar + storage request withdrawn in the PJM interconnection queue, in Rock Island County, Illinois, connecting to ComEd.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Mar 2021 (completed)
  2. Withdrawn / abandonedDec 2024 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
AG2-517
Grid region
PJM (Mid-Atlantic, Midwest)
Utility / transmission owner
ComEd
Connection point (POI)
Cordova Energy Center 345kV
Location
Rock Island County, Illinois
Technology
Solar: 120 MW Β· Battery
Total requested
120 MW
Service type
Network resource (NRIS)
Study phase
Feasibility Study
Queue status
Withdrawn
Entered queue
31 March 2021
Proposed online date
October 2023
Withdrawn
December 2024

Location

Marker shows the centre of Rock Island County; the queue data does not give exact sites.

Power plants in Illinois Β· Transmission lines in Illinois

Other requests in Rock Island County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem