NUCLEAR Β· PJMNuclear project X3-046, Rock Island County
Nuclear project X3-046, Rock Island County is a 32.0 MW nuclear request withdrawn in the PJM interconnection queue, in Rock Island County, Illinois, connecting to ComEd.
Queue statusWithdrawn / abandoned
- PlanningQueued Sep 2011 (completed)
- Withdrawn / abandonedMar 2013 (project stopped here)
- Consented (not reached)
- Construction (not reached)
- Operating (not reached)
- Closed (not reached)
Request details
- Queue ID
- X3-046
- Grid region
- PJM (Mid-Atlantic, Midwest)
- Utility / transmission owner
- ComEd
- Connection point (POI)
- Quad Cities
- Location
- Rock Island County, Illinois
- Technology
- Nuclear: 32.0 MW
- Total requested
- 32.0 MW
- Service type
- Network resource (NRIS)
- Study phase
- Available studies: Feasibility Study
- Queue status
- Withdrawn
- Entered queue
- 14 September 2011
- Proposed online date
- June 2014
- Withdrawn
- March 2013
Location
Marker shows the centre of Rock Island County; the queue data does not give exact sites.
Other requests in Rock Island County
- Battery storage project J3525, Rock Island CountyBattery storage Β· 300 MW Β· in study
- Onshore wind project J4112, Rock Island CountyOnshore wind Β· 300 MW Β· in study
- Beacon SolarSolar Β· 260 MW Β· in study
- Battery storage project J3660, Rock Island CountyBattery storage Β· 200 MW Β· in study
- Solar + storage project J2738, Rock Island CountySolar + storage Β· 128 MW Β· in study
- Battery storage project AG2-675, Rock Island CountyBattery storage Β· 80.0 MW Β· in study
- Battery storage project J2552, Rock Island CountyBattery storage Β· 80.0 MW Β· in study
- Quad Cities - Units 1 & 2Nuclear Β· 140 MW Β· built
- Nuclear project J372, Rock Island CountyNuclear Β· 1,373 MW Β· withdrawn
- Solar + storage project AG2-517, Rock Island CountySolar + storage Β· 120 MW Β· withdrawn
- Solar project J1420, Rock Island CountySolar Β· 48.0 MW Β· withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem