ONSHORE WIND · PJM

Shady Oaks Wind Power Project

Shady Oaks Wind Power Project is a 106 MW onshore wind request with a signed interconnection agreement in the PJM interconnection queue, in Lee County, Illinois, connecting to ComEd.

Queue statusConsented
  1. PlanningQueued Mar 2018 (completed)
  2. Consented (current stage)
  3. Construction (not yet reached)
  4. OperatingTarget Dec 2027 (not yet reached)
  5. Closed (not yet reached)

Request details

Queue ID
AD2-134
Grid region
PJM (Mid-Atlantic, Midwest)
Utility / transmission owner
ComEd
Connection point (POI)
Shady Oaks
Location
Lee County, Illinois
Technology
Wind: 106 MW
Total requested
106 MW
Service type
Network resource (NRIS)
Study phase
Available studies: Feasibility Study, System Impact Study, Facilities Study; Interim/Interconnection Service Agreement:
Queue status
Active
Entered queue
25 March 2018
Proposed online date
December 2027

Location

Marker shows the centre of Lee County; the queue data does not give exact sites.

Power plants in Illinois · Transmission lines in Illinois

Other requests in Lee County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem