SOLAR · PJM

Kankakee Solar

Kankakee Solar is a 144 MW solar request in interconnection study in the PJM interconnection queue, in Kankakee County, Illinois, connecting to ComEd.

Queue statusIn planning
  1. PlanningQueued Feb 2020 (current stage)
  2. Consented (not yet reached)
  3. Construction (not yet reached)
  4. OperatingTarget May 2021 (not yet reached)
  5. Closed (not yet reached)

Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.

Request details

Queue ID
AF2-095
Grid region
PJM (Mid-Atlantic, Midwest)
Utility / transmission owner
ComEd
Developer
AEUG Kankakee Solar, LLC
Connection point (POI)
Davis Creek 138 kV
Location
Kankakee County, Illinois
Technology
Solar: 144 MW
Total requested
144 MW
Service type
Network resource (NRIS)
Study phase
Available studies: Feasibility Study, System Impact Study
Queue status
Active
Entered queue
13 February 2020
Proposed online date
May 2021

Location

Marker shows the centre of Kankakee County; the queue data does not give exact sites.