ONSHORE WIND · PJMLower Crossing Wind
Lower Crossing Wind is a 200 MW onshore wind request suspended in the PJM interconnection queue, in Kankakee County, Illinois, connecting to ComEd.
Queue statusPaused / redesign
- PlanningQueued Jan 2018 (current stage)
- Consented (not yet reached)
- Construction (not yet reached)
- OperatingTarget Nov 2026 (not yet reached)
- Closed (not yet reached)
Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.
Request details
- Queue ID
- AD2-047
- Grid region
- PJM (Mid-Atlantic, Midwest)
- Utility / transmission owner
- ComEd
- Connection point (POI)
- Davis Creek 138 kV
- Location
- Kankakee County, Illinois
- Technology
- Wind: 200 MW
- Total requested
- 200 MW
- Service type
- Network resource (NRIS)
- Study phase
- Available studies: Feasibility Study, System Impact Study, Facilities Study; Interim/Interconnection Service Agreement:
- Queue status
- Suspended
- Entered queue
- 31 January 2018
- Proposed online date
- November 2026
Location
Marker shows the centre of Kankakee County; the queue data does not give exact sites.
Other requests in Kankakee County
- Heritage Prairie WindOnshore wind · 850 MW · agreement signed
- Heritage Prairie SolarSolar · 150 MW · agreement signed
- Heritage Prairie SolarSolar · 150 MW · agreement signed
- Staley SolarSolar · 50.0 MW · agreement signed
- Staley SolarSolar · 20.0 MW · agreement signed
- Solar + storage project AH2-363, Kankakee CountySolar + storage · 200 MW · in study
- Solar project AI1-148, Kankakee CountySolar · 164 MW · in study
- Kankakee SolarSolar · 144 MW · in study
- Grand Marsh SolarSolar · 100 MW · in study
- Solar project AG2-585, Kankakee CountySolar · 55.0 MW · in study
- Solar project AI2-014, Kankakee CountySolar · 37.9 MW · in study
- Kelly Creek Wind FarmOnshore wind · 175 MW · built
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem