🔌 EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more → Skip to main content

United States › Grid › Interconnection queues › Illinois

ONSHORE WIND · PJM

Kelly Creek Wind Farm

Kelly Creek Wind Farm is a 175 MW onshore wind request built and operating in the PJM interconnection queue, in Kankakee County, Illinois, connecting to ComEd.

Queue statusOperating
  1. PlanningQueued May 2007 (completed)
  2. ConsentedOct 2014 (completed)
  3. Construction (completed)
  4. OperatingNov 2016 (current stage)
  5. Closed (not yet reached)

Request details

Queue ID
S37
Grid region
PJM (Mid-Atlantic, Midwest)
Utility / transmission owner
ComEd
Connection point (POI)
Kankakee 138kV
Location
Kankakee County, Illinois
Technology
Wind: 175 MW
Total requested
175 MW
Service type
Network resource (NRIS)
Study phase
Available studies: Feasibility Study, System Impact Study, Facilities Study; Interim/Interconnection Service Agreement:
Queue status
Operational
Entered queue
7 May 2007
Agreement signed
14 October 2014
Proposed online date
December 2016
Came online
November 2016

Location

Marker shows the centre of Kankakee County; the queue data does not give exact sites.

Power plants in Illinois · Transmission lines in Illinois

Other requests in Kankakee County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem