Staley Solar

Staley Solar is a 50.0 MW solar request with a signed interconnection agreement in the PJM interconnection queue, in Kankakee County, Illinois, connecting to ComEd.

Queue statusConsented
  1. PlanningQueued Mar 2017 (completed)
  2. Consented (current stage)
  3. Construction (not yet reached)
  4. OperatingTarget Sep 2027 (not yet reached)
  5. Closed (not yet reached)

Request details

Queue ID
AC2-154
Grid region
PJM (Mid-Atlantic, Midwest)
Utility / transmission owner
ComEd
Connection point (POI)
Davis Creek 138kV
Location
Kankakee County, Illinois
Technology
Solar: 50.0 MW
Total requested
50.0 MW
Service type
Network resource (NRIS)
Study phase
Available studies: Feasibility Study, System Impact Study, Facilities Study; Interim/Interconnection Service Agreement:
Queue status
Active
Entered queue
29 March 2017
Proposed online date
September 2027

Location

Marker shows the centre of Kankakee County; the queue data does not give exact sites.