🔌 EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more → Skip to main content

United States › Grid › Interconnection queues › Illinois

ONSHORE WIND · MISO

Onshore wind project J3602, Mclean County

Onshore wind project J3602, Mclean County is a 110 MW onshore wind request in interconnection study in the MISO interconnection queue, in Mclean County, Illinois, connecting to AMEREN ILLINOIS.

Queue statusIn planning
  1. PlanningQueued Apr 2024 (current stage)
  2. Consented (not yet reached)
  3. Construction (not yet reached)
  4. OperatingTarget Apr 2028 (not yet reached)
  5. Closed (not yet reached)

Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.

Request details

Queue ID
J3602
Grid region
MISO (Midcontinent)
Utility / transmission owner
AMEREN ILLINOIS
Connection point (POI)
Other_
Location
Mclean County, Illinois
Technology
Wind: 110 MW
Total requested
110 MW
Service type
Network resource (NRIS)
Study phase
Study Phase: DPP 1
Queue status
Active
Entered queue
17 April 2024
Proposed online date
April 2028

Location

Marker shows the centre of Mclean County; the queue data does not give exact sites.

Power plants in Illinois · Transmission lines in Illinois

Other requests in Mclean County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem