ONSHORE WIND · MISO

Onshore wind project J3566, Mclean County

Onshore wind project J3566, Mclean County is a 198 MW onshore wind request in interconnection study in the MISO interconnection queue, in Mclean County, Illinois, connecting to AMEREN ILLINOIS.

Queue statusIn planning
  1. PlanningQueued Apr 2024 (current stage)
  2. Consented (not yet reached)
  3. Construction (not yet reached)
  4. OperatingTarget Aug 2028 (not yet reached)
  5. Closed (not yet reached)

Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.

Request details

Queue ID
J3566
Grid region
MISO (Midcontinent)
Utility / transmission owner
AMEREN ILLINOIS
Connection point (POI)
Other_
Location
Mclean County, Illinois
Technology
Wind: 198 MW
Total requested
198 MW
Service type
Energy only (ERIS)
Study phase
Study Phase: DPP 1
Queue status
Active
Entered queue
18 April 2024
Proposed online date
August 2028

Location

Marker shows the centre of Mclean County; the queue data does not give exact sites.

Power plants in Illinois · Transmission lines in Illinois

Other requests in Mclean County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem