United States › Grid › Interconnection queues › Illinois

SOLAR · MISO

Solar project J641, Morgan County

Solar project J641, Morgan County is a 140 MW solar request with a signed interconnection agreement in the MISO interconnection queue, in Morgan County, Illinois.

Queue statusConsented
  1. PlanningQueued May 2016 (completed)
  2. ConsentedOct 2018 (current stage)
  3. Construction (not yet reached)
  4. OperatingNov 2024 (not yet reached)
  5. Closed (not yet reached)

Request details

Queue ID
J641
Grid region
MISO (Midcontinent)
Connection point (POI)
Line tap of Meredoisa sub to Jacksonville Industrial Park 138kv
Location
Morgan County, Illinois
Technology
Solar: 140 MW
Total requested
140 MW
Study phase
GIA
Queue status
Active
Entered queue
9 May 2016
Agreement signed
31 October 2018
Proposed online date
June 2021
Came online
November 2024

Location

Marker shows the centre of Morgan County; the queue data does not give exact sites.

Power plants in Illinois · Transmission lines in Illinois

Other requests in Morgan County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem