United States βΊ Grid βΊ Interconnection queues βΊ Illinois
ONSHORE WIND Β· MISOOnshore wind project J318, Morgan County
Onshore wind project J318, Morgan County is a 30.0 MW onshore wind request withdrawn in the MISO interconnection queue, in Morgan County, Illinois.
Queue statusWithdrawn / abandoned
- PlanningQueued Dec 2013 (completed)
- Withdrawn / abandonedMay 2014 (project stopped here)
- ConsentedMay 2014 (not reached)
- Construction (not reached)
- Operating (not reached)
- Closed (not reached)
Request details
- Queue ID
- J318
- Grid region
- MISO (Midcontinent)
- Connection point (POI)
- SW corner of Berlin Tower Rd & Huff Road
- Location
- Morgan County, Illinois
- Technology
- Wind: 30.0 MW
- Total requested
- 30.0 MW
- Queue status
- Withdrawn
- Entered queue
- 18 December 2013
- Agreement signed
- 15 May 2014
- Proposed online date
- September 2017
- Withdrawn
- May 2014
Location
Marker shows the centre of Morgan County; the queue data does not give exact sites.
Other requests in Morgan County
- Onshore wind project J750, Morgan CountyOnshore wind Β· 150 MW Β· under construction
- Onshore wind project J1289, Morgan CountyOnshore wind Β· 200 MW Β· agreement signed
- Solar project J641, Morgan CountySolar Β· 140 MW Β· agreement signed
- Solar project J2908, Morgan CountySolar Β· 30.0 MW Β· in study
- Onshore wind project J757, Morgan CountyOnshore wind Β· 304 MW Β· built
- Battery storage project J3360, Morgan CountyBattery storage Β· 250 MW Β· withdrawn
- Onshore wind project J835, Morgan CountyOnshore wind Β· 200 MW Β· withdrawn
- Coal project J239, Morgan CountyCoal Β· 200 MW Β· withdrawn
- Onshore wind project G908, Morgan CountyOnshore wind Β· 150 MW Β· withdrawn
- Solar project J3684, Morgan CountySolar Β· 100 MW Β· withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem