United States β€Ί Grid β€Ί Interconnection queues β€Ί Illinois

ONSHORE WIND Β· MISO

Onshore wind project G908, Morgan County

Onshore wind project G908, Morgan County is a 150 MW onshore wind request withdrawn in the MISO interconnection queue, in Morgan County, Illinois.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Mar 2009 (completed)
  2. Withdrawn / abandonedDec 2011 (project stopped here)
  3. ConsentedDec 2011 (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
G908
Grid region
MISO (Midcontinent)
Connection point (POI)
Havana - E Springfield 138 kV
Location
Morgan County, Illinois
Technology
Wind: 150 MW
Total requested
150 MW
Study phase
SPA - SIS
Queue status
Withdrawn
Entered queue
23 March 2009
Agreement signed
29 December 2011
Proposed online date
November 2009
Withdrawn
December 2011

Location

Marker shows the centre of Morgan County; the queue data does not give exact sites.

Power plants in Illinois Β· Transmission lines in Illinois

Other requests in Morgan County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem