United States β€Ί Grid β€Ί Interconnection queues β€Ί Illinois

ONSHORE WIND Β· MISO

Onshore wind project J835, Morgan County

Onshore wind project J835, Morgan County is a 200 MW onshore wind request withdrawn in the MISO interconnection queue, in Morgan County, Illinois, connecting to AMEREN ILLINOIS.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Jun 2017 (completed)
  2. Withdrawn / abandonedApr 2019 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
J835
Grid region
MISO (Midcontinent)
Utility / transmission owner
AMEREN ILLINOIS
Connection point (POI)
Meredosia - Austin 345kV Line
Location
Morgan County, Illinois
Technology
Wind: 200 MW
Total requested
200 MW
Service type
Network resource (NRIS)
Study phase
Study Phase: GIA; Post GIA Status: Not Started
Queue status
Withdrawn
Entered queue
16 June 2017
Proposed online date
July 2020
Withdrawn
April 2019

Location

Marker shows the centre of Morgan County; the queue data does not give exact sites.

Power plants in Illinois Β· Transmission lines in Illinois

Other requests in Morgan County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem