United States › Grid › Interconnection queues › Texas

OCTARY USA · INTERCONNECTION QUEUES

Withdrawn queue requests in Texas (2020 requests)

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown558,621 MW
Active in queue28.9 GW115 requests
Agreement signed14.9 GW54 requests
Withdrawn558,621 MW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

55 requests · page 1 of 2
ProjectCapacityStatusLocationRegionQueuedOnline
Gibbons Creek TEERP
Coal · TEERP Power Station LLC
420 MWWithdrawn / abandoned Grimes, TXERCOT Apr 2020target 2020
Plum Creek Solar I
Solar · PLUM CREEK SOLAR I, LLC
400 MWWithdrawn / abandoned Grimes, TXERCOT Jun 2020target 2023
Solar project GEN-2020-068, Terry County
Solar
400 MWWithdrawn / abandoned Terry, TXSPP Apr 2020target 2026
Sibyl Power Station
Gas · WattBridge Energy, LLC
299 MWWithdrawn / abandoned Fort Bend, TXERCOT Sep 2020target 2025
Onshore wind project J1812, Chambers County
Onshore wind
294 MWWithdrawn / abandoned Chambers, TXMISO Jun 2020target 2024
Onshore wind project GEN-2020-066, Hockley County
Onshore wind
254 MWWithdrawn / abandoned Hockley, TXSPP Apr 2020target 2026
Neal Solar
Solar · SolarGen Resources LLC
252 MWWithdrawn / abandoned Wharton, TXERCOT Nov 2020target 2023
Langer Solar
Solar · Langer Solar LLC
250 MWWithdrawn / abandoned Bosque, TXERCOT Jun 2020target 2027
Cottage Meadow Storage
Other · KCE TX 18, LLC
209 MWWithdrawn / abandoned Cameron, TXERCOT Jan 2020target 2021
Egret Hill Storage
Other · Coyote Crossing LLC
206 MWWithdrawn / abandoned Hunt, TXERCOT Sep 2020target 2021
Thunderbird Solar SLF
Solar · Thunderbird Solar, LLC
204 MWWithdrawn / abandoned Milam, TXERCOT Dec 2020target 2024
Flagtail Batt
Other · Flagtail LLC
204 MWWithdrawn / abandoned Grimes, TXERCOT Apr 2020target 2022
BRP Lyra BESS
Other · BRP Lyra BESS LLC
203 MWWithdrawn / abandoned Pecos, TXERCOT Jun 2020target 2022
Corbin Grid BESS
Other · Corbin Grid, LLC
203 MWWithdrawn / abandoned Fort Bend, TXERCOT Aug 2020target 2026
Wekiva Grid
Battery storage · Wekiva Grid, LLC
203 MWWithdrawn / abandoned Titus, TXERCOT Aug 2020target 2024
Sibyl Energy Storage
Other · WattBridge Energy, LLC
202 MWWithdrawn / abandoned Fort Bend, TXERCOT Dec 2020target 2024
Topaz Energy Storage
Other · WattBridge Energy, LLC
202 MWWithdrawn / abandoned Galveston, TXERCOT Dec 2020target 2025
Clybourn Solar
Solar · Leeward Renewable Energy Development, LLC
202 MWWithdrawn / abandoned Matagorda, TXERCOT May 2020target 2022
Milwaukee Solar
Solar · Leeward Renewable Energy Development, LLC
202 MWWithdrawn / abandoned Matagorda, TXERCOT Nov 2020target 2022
Raoul Solar
Solar · Leeward Renewable Energy Development, LLC
201 MWWithdrawn / abandoned Fort Bend, TXERCOT Oct 2020target 2023
Elston Solar
Solar · Leeward Renewable Energy Development, LLC
201 MWWithdrawn / abandoned Matagorda, TXERCOT May 2020target 2023
Girasol
Solar · OCI SOLAR POWER
200 MWWithdrawn / abandoned Zavala, TXERCOT May 2020target 2022
Bonita Creek Solar
Solar · Invenergy Solar Development North America LLC
200 MWWithdrawn / abandoned Atascosa, TXERCOT Dec 2020target 2026
Delilah Solar 3
Solar
200 MWWithdrawn / abandoned Lamar, TXERCOT Jun 2020
Brangus Storage
Other · 245CK 8me LLC
200 MWWithdrawn / abandoned Kinney, TXERCOT Jan 2020target 2023
Seaside Solar
Solar · Seadrift Solar
200 MWWithdrawn / abandoned Calhoun, TXERCOT Dec 2020target 2024
Hopkins BESS
Other · Hopkins Energy, LLC
188 MWWithdrawn / abandoned Hopkins, TXERCOT Nov 2020target 2023
Onshore wind project GEN-2020-005, Carson County
Onshore wind
150 MWWithdrawn / abandoned Carson, TXSPP Mar 20202023
Evergreen Solar
Solar · Bucks Bayou LLC
150 MWWithdrawn / abandoned Matagorda, TXERCOT Dec 2020target 2025
Nolan Solar
Solar · Tenaska Solar XVII, LLC
150 MWWithdrawn / abandoned Nolan, TXERCOT Jan 2020target 2023
SkySealy
Gas · Sky Global Power Two, LLC
149 MWWithdrawn / abandoned Austin, TXERCOT Apr 2020target 2025
Ponil Solar
Solar · Innovative Solar 377, LLC
145 MWWithdrawn / abandoned Childress, TXERCOT Feb 2020target 2025
Barrel Summit Storage
Other · KCE TX 14, LLC
117 MWWithdrawn / abandoned Ellis, TXERCOT Jun 2020target 2022
Cone Mountain Batt
Other · Ramsay Draw LLC
103 MWWithdrawn / abandoned Brewster, TXERCOT Sep 2020target 2021
Vorsavio Grid BESS
Other · Vorsavio Grid, LLC
101 MWWithdrawn / abandoned Webb, TXERCOT Oct 2020target 2024
Beachwood Energy Storage (Mark One BESS)
Other · Mark One Energy Storage, LLC
101 MWWithdrawn / abandoned Brazoria, TXERCOT Dec 2020target 2024
Delilah Solar 4
Solar
90.0 MWWithdrawn / abandoned Lamar, TXERCOT Jul 2020
SBranch Expansion Solar
Solar · CG Wharton County LLC
76.0 MWWithdrawn / abandoned Wharton, TXERCOT Oct 2020target 2022
Solar project GEN-2020-017, Lamb County
Solar
74.9 MWWithdrawn / abandoned Lamb, TXSPP Apr 20202025
Kirkwall Solar
Solar · ABEI ENERGY
73.1 MWWithdrawn / abandoned Williamson, TXERCOT Nov 2020target 2023
Battery storage project GEN-2020-055, Bowie County
Battery storage
71.0 MWWithdrawn / abandoned Bowie, TXSPP Apr 20202025
Hathor Solar
Solar · ABEI ENERGY & INFRASTRUCTURE
67.6 MWWithdrawn / abandoned Hunt, TXERCOT Sep 2020target 2023
Blue Sky Solar
Solar · Blue Sky Solar
65.0 MWWithdrawn / abandoned Crockett, TXERCOT Feb 2020target 2022
Lund Storage
Other · RRE POWER STORAGE 1 LLC
60.0 MWWithdrawn / abandoned Travis, TXERCOT Apr 2020target 2023
Buckeye Corpus Fuels Solar
Solar · BAES INFRASTRUCTURE CORPUS CHRISTI SOLAR LLC
57.6 MWWithdrawn / abandoned Nueces, TXERCOT Aug 2020target 2025
Endurance Park Storage 2
Other · KCE TX 22, LLC
52.3 MWWithdrawn / abandoned Scurry, TXERCOT Apr 2020target 2022
Belding 2 Batt
Other · Triple Butte II LLC
51.5 MWWithdrawn / abandoned Pecos, TXERCOT Mar 2020target 2024
Brotman Energy Storage
Other · WattBridge Energy, LLC
50.8 MWWithdrawn / abandoned Brazoria, TXERCOT Dec 2020target 2023
Pisgah Ridge Solar 50MW
Solar · Duke Energy Renewables Solar, LLC
50.6 MWWithdrawn / abandoned Navarro, TXERCOT Jul 2020target 2022
Boca Chica Solar
Solar · Tenaska Solar XVIII, LLC
50.0 MWWithdrawn / abandoned Cameron, TXERCOT Jan 2020target 2023
Page 1 of 2

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines · Planned power plants (EIA)