United States › Grid › Interconnection queues

OCTARY USA · INTERCONNECTION QUEUES

Withdrawn queue requests in ERCOT (Texas) (2024 requests)

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown5010.0 GW
Active in queue104.7 GW436 requests
Agreement signed16.8 GW70 requests
Withdrawn5010.0 GW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

50 requests
ProjectCapacityStatusLocationRegionQueuedOnline
Perseus Gas
Gas · Engie Flexible Generation NA LLC
1,057 MWWithdrawn / abandoned ERCOT Aug 2024target 2028
ELTEX Power Station
Gas · ELTEX Power Station LLC
488 MWWithdrawn / abandoned Austin, TXERCOT Sep 2024target 2027
Denver City - Mustang - Gas
Gas · Golden Spread Electric Cooperative, Inc.
472 MWWithdrawn / abandoned Yoakum, TXERCOT Dec 2024target 2029
Kiskadee Trail Storage SLF
Battery storage · Kiskadee Trail Storage, LLC
406 MWWithdrawn / abandoned ERCOT Oct 2024target 2029
Kiskadee Trail Solar SLF
Solar · Kiskadee Trail Solar, LLC
406 MWWithdrawn / abandoned ERCOT Oct 2024target 2029
Austin Bayou Solar II
Solar · Austin Bayou Solar, LLC
402 MWWithdrawn / abandoned Brazoria, TXERCOT Mar 2024target 2027
Firefly Power
Battery storage · Firefly Power LLC
401 MWWithdrawn / abandoned Tarrant, TXERCOT Feb 2024target 2027
Savanna Prairie Solar
Solar · Savanna Prairie Solar, LLC
355 MWWithdrawn / abandoned ERCOT Oct 2024target 2028
Adams Brook Storage
Other · Adams Creek Solar Project, LLC
314 MWWithdrawn / abandoned Wilbarger, TXERCOT Feb 2024target 2027
Fletcher BESS
Battery storage · Archer Energy Center, LLC
310 MWWithdrawn / abandoned ERCOT Jul 2024target 2027
Box Canyon Energy Storage
Other · Box Canyon Energy Storage Project, LLC
306 MWWithdrawn / abandoned Callahan, TXERCOT Jan 2024target 2027
Goose Foot Energy Storage
Battery storage · Goose Foot Energy Storage Project, LLC
306 MWWithdrawn / abandoned ERCOT Dec 2024target 2028
Mariette Solar
Solar · Mariette Solar LLC
301 MWWithdrawn / abandoned Wichita, TXERCOT Oct 2024target 2028
Sentinel Solar
Solar · Alamo Ranch Solar Project, LLC
271 MWWithdrawn / abandoned ERCOT Oct 2024target 2029
Rippling Curve Peaking Power
Gas · OxyVinyls LP
208 MWWithdrawn / abandoned Harris, TXERCOT Sep 2024target 2029
Shoe Bar Solar
Solar · Oberon Solar V, LLC
206 MWWithdrawn / abandoned ERCOT Oct 2024target 2028
Tierra Alta Storage SLF
Battery storage · ET Fuels US Inc.
205 MWWithdrawn / abandoned Schleicher, TXERCOT Dec 2024target 2028
North Leona Solar
Solar · Orion US Land Holding Co LLC
205 MWWithdrawn / abandoned Frio, TXERCOT Jul 2024target 2028
Medellin Road BESS
Other · Horizon Energy Storage Green Field
203 MWWithdrawn / abandoned Harris, TXERCOT Jan 2024target 2027
HyFuels Iron Horse Solar
Solar · HyFuels Green Lake Solar LLC
201 MWWithdrawn / abandoned Victoria, TXERCOT Mar 2024target 2026
Ridley Solar SLF
Solar · Ridley Solar Project, LLC
201 MWWithdrawn / abandoned ERCOT Jul 2024target 2029
Altita Solar
Solar · ACE DevCo NC, LLC
182 MWWithdrawn / abandoned ERCOT Feb 2024target 2028
South Loop Energy Center
Battery storage · Concurrent Holdco LLC
161 MWWithdrawn / abandoned ERCOT May 2024target 2028
Villarreal Solar SLF
Solar · Orion US Land Holding Co LLC
153 MWWithdrawn / abandoned Webb, TXERCOT May 2024target 2028
Veco Ranch Solar SLF
Solar · Orion US Land Holding Co LLC
153 MWWithdrawn / abandoned Webb, TXERCOT Jul 2024target 2029
Gail Mountain Solar
Solar · Gail Mountain Solar, LLC
152 MWWithdrawn / abandoned ERCOT Jan 2024target 2026
Gail Mountain Storage
Battery storage · Gail Mountain Solar, LLC
152 MWWithdrawn / abandoned ERCOT Feb 2024target 2026
Olsovksy Storage
Battery storage · BT Sky Storage, LLC
151 MWWithdrawn / abandoned Hill, TXERCOT Jan 2024target 2026
Augite Storage
Battery storage · BT Augite Storage, LLC
151 MWWithdrawn / abandoned Starr, TXERCOT Feb 2024target 2027
Larimar Solar
Solar · BT S7 Solar, LLC
151 MWWithdrawn / abandoned Bee, TXERCOT Jan 2024target 2026
Paddlewheel Solar SLF
Solar · Paddlewheel Solar, LLC
150 MWWithdrawn / abandoned ERCOT Jun 2024target 2027
Sugar Land Power Plant
Gas · Imperial Power Plant, LLC
148 MWWithdrawn / abandoned Fort Bend, TXERCOT Aug 2024target 2027
Savanna Prairie Storage
Battery storage · Savanna Prairie Storage, LLC
114 MWWithdrawn / abandoned ERCOT Oct 2024target 2028
Bluewind Energy Center
Battery storage · Bluewind Energy Center, LLC
103 MWWithdrawn / abandoned Atascosa, TXERCOT Feb 2024target 2026
North Leona BESS
Battery storage · Orion US Land Holding Co LLC
102 MWWithdrawn / abandoned Frio, TXERCOT Aug 2024target 2028
Larimar Storage
Battery storage · BT S7 Solar, LLC
101 MWWithdrawn / abandoned Bee, TXERCOT Jan 2024target 2026
Texas Sage Solar SLF
Solar · Texas Sage Solar Project, LLC
101 MWWithdrawn / abandoned ERCOT Apr 2024target 2028
Kobernat Solar
Solar · BT Kobernat Solar, LLC
101 MWWithdrawn / abandoned Starr, TXERCOT Feb 2024target 2026
Mica BESS
Battery storage · Mica BESS LLC
80.4 MWWithdrawn / abandoned Harris, TXERCOT Nov 2024target 2026
Gold Coin Storage
Battery storage · Grenergy USA
73.0 MWWithdrawn / abandoned ERCOT Nov 2024target 2027
Kobernat Storage
Battery storage · BT Kobernat Solar, LLC
51.5 MWWithdrawn / abandoned Starr, TXERCOT Feb 2024target 2026
Paddlewheel BESS SLF
Battery storage · Paddlewheel Solar, LLC
50.0 MWWithdrawn / abandoned ERCOT Jun 2024target 2027
Kiskadee Trail Solar
Solar · Kiskadee Solar, LLC
40.9 MWWithdrawn / abandoned ERCOT Jun 2024target 2027
Kiskadee Trail Storage
Battery storage · Kiskadee Storage, LLC
40.8 MWWithdrawn / abandoned ERCOT Jun 2024target 2027
Arroyo Storage (Placeholder)
Other · BT Cantwell Solar, LLC
35.3 MWWithdrawn / abandoned Cameron, TXERCOT Jan 2024target 2024
Mills Prairie Solar
Solar · Mills Solar, LLC
33.0 MWWithdrawn / abandoned Navarro, TXERCOT Nov 2024target 2027
Mills Prairie Storage
Battery storage · Mills Storage, LLC
33.0 MWWithdrawn / abandoned Navarro, TXERCOT Nov 2024target 2027
Nightfall BESS SLF
Battery storage · BDPU Solar Nightfall, LLC
11.0 MWWithdrawn / abandoned Uvalde, TXERCOT May 2024target 2026
Jourdanton BESS
Battery storage · Jourdanton BESS LLC
9.8 MWWithdrawn / abandoned ERCOT Nov 2024target 2025
E Babe Smith Solar
Solar · Hwy 183 Solar LLC
7.6 MWWithdrawn / abandoned ERCOT Apr 2024target 2024

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines · Planned power plants (EIA)