πŸ”Œ EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more β†’ Skip to main content

United States β€Ί Grid β€Ί Interconnection queues

BATTERY STORAGE Β· ERCOT

Jourdanton BESS

Jourdanton BESS is a 9.8 MW battery storage request withdrawn in the ERCOT interconnection queue.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Nov 2024 (completed)
  2. Withdrawn / abandoned (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
27INR0433
Grid region
ERCOT (Texas)
Developer
Jourdanton BESS LLC
Connection point (POI)
Station Name: Jourdanton_x000D_ Station Code: JOURDNTN_x000D_ Load/Load Transformer Name: TR1X _x000D_ PTI BUS number: 8607 _x000D_ Voltage in kV: 69 kV
Technology
Battery: 9.8 MW
Total requested
9.8 MW
Study phase
No MRD
Queue status
Withdrawn
Entered queue
7 November 2024
Proposed online date
December 2025

Location

No county location in the queue data.

Power plants in Β· Transmission lines in

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem